Narangba station temporary platform changes

Started by ozbob, February 07, 2013, 15:36:22 PM

Previous topic - Next topic

ozbob

http://jp.translink.com.au/travel-information/service-updates/details/1358822268

Narangba station temporary platform changes

Last updated: 2.35pm Tuesday 5 February 2013

As part of the Narangba station upgrade project, Queensland Rail is undertaking improvement works to provide better facilities.

From Tuesday 19 February until Monday 25 March, there'll be temporary platform changes and closures due to upgrade works.

Narangba station temporary platform change

From Tuesday 19 February until Monday 4 March

    all inbound services to the city will continue to depart from platform one during the morning peak.
    from 9.30am until last service, all inbound services to the city will leave from platform two.

Narangba station platform closure

From Monday 4 March until Monday 25 March 2013, platform one will be closed.

All inbound services will depart from platform two, instead of platform one.
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  X   Mastodon  BlueSky

ozbob

http://jp.translink.com.au/travel-information/service-updates/details/1358822268

Narangba station temporary platform changes

Last updated: 1.16pm Monday 11 February 2013

As part of the Narangba station upgrade project, Queensland Rail is undertaking improvement works to provide better facilities.

From Tuesday 19 February until Monday 25 March, there'll be temporary platform changes and closures due to upgrade works.

Narangba station temporary platform change

From Tuesday 19 February until Monday 4 March

    all inbound services to the city will continue to depart from platform one during the morning peak.
    from 9.30am until last service, all inbound services to the city will leave from platform two.

Narangba station platform closure

From Monday 4 March until Monday 25 March 2013, platform one will be closed.

All inbound services will depart from platform two, instead of platform one.
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  X   Mastodon  BlueSky

Fares_Fair


http://www.couriermail.com.au/questnews/moreton/narangba-train-station-has-been-upgraded-but-is-there-enough-parking/story-fn8m0yu3-1226653985744

Quote

Narangba train station has been upgraded, but is there enough parking?

Jamie-Leigh Mason, Caboolture Shire Herald•
Quest Newspapers•
May 31, 201312:00AM

The Minister for Transport and Main Roads Scott Emerson with Acting CEO of Queensland Rail Jim Benstead at the refurbished Narangba Train Station at Narangba.
Source: Quest Newspapers

Upgrades to Narangba train station will be completed next week, with the $26 million price tag improving disabled access and adding 20 parking spaces at the station.

Transport and Main Roads Minister Scott Emerson said Narangba was one of the 30 busiest stations in Queensland and expected it be even busier in the future.

``There is already 1500 people using this station per day,'' Mr Emerson said.

``And I expect it (number of commuters) to increase even more with these upgrades and future development.''

Despite the rapid growth of Narangba and nearby suburbs such as Dakabin, Mr Emerson said he felt 20 additional car parks, to make the total 380, was sufficient with the upgrades including a bicycle enclosure and a bus interchange.

``It is always a challenge trying to get to stations and a lot of people walk, ride their bike or find other ways. We've put disabled carparking spaces near the ramp as well,'' he said.

Queensland Rail chief executive Jim Benstead said he hoped the improved station, which included lifts and ramps, would lead to further investment in the area.

Project manager for the Narangba upgrade Andrew Gibson said the upgrades, which started in February 2012, would be completed by June 12.

``The platform has been raised which allows wheelchair access straight on the train and minimises the gap,'' Mr Gibson said.
Regards,
Fares_Fair


🡱 🡳