Re: Monthly line specific on-time running and reliability February 2021
« Reply #1 on: April 10, 2021, 01:04:07 PM »
Individual lines

Spreadsheet: https://backontrack.org/docs/qr/monthly_otr/2021/feb/all_lines_monthly_apr19tofeb21.ods























Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #2 on: April 10, 2021, 01:04:35 PM »
Combining the Queensland Rail total (aggregate) results on the same axes allows a better appreciation of what is happening.

Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #3 on: April 10, 2021, 01:05:22 PM »
Spreadsheet --> https://backontrack.org/docs/qr/monthly_otr/2021/feb/QRsummary_apr2019_feb2021.ods









« Last Edit: April 10, 2021, 01:11:57 PM by ozbob »
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #4 on: April 11, 2021, 04:55:35 AM »
As patronage returns to the network we are seeing signs of loss of OTR reliability.

Cleveland ( ), Caboolture and Beenleigh lines, not the best.

Even aggregate (total) - all lines combined,  Citytrain has dropped off significantly for the first time since March 2020

Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #5 on: April 11, 2021, 07:20:58 AM »
Sent to all outlets:

11th April 2021

Update on on-time running performance for Citytrain Queensland Rail Month of February 2021

Services, including peak and off-peak, are measured as on-time when they arrive within three minutes and 59 seconds of their scheduled time, except for the interurban services viz. Gold Coast, Rosewood and Sunshine Coast which are measured as on time if they arrive within 5 minutes and 59 seconds.
 
Target is services > 95% on time
FMA = force majeure adjusted
CI = customer impact (what passengers actually experience)
CP = combined peaks

Overall FMA on-time running (OTR) for February 2021 was below the target of 95%. Cleveland, Beenleigh and Caboolture lines particularly the OTR performance is poor and this is dragging down the total (aggregate) of all lines. See graphs below. This is the first time that Citytrain has dropped below the target of 95% for force majeure adjusted results since March 2020. Customer impact, what passengers actually experience, is worse than that.

The Cleveland line is a single line between Manly and Cleveland and this makes it difficult for Queensland Rail to maintain the peak timetable.  Projections in the 2017 Cross River Rail business case for 10 trains per hour on the Cleveland line in the morning peak were and are non deliverable unless there are significant upgrades to improve capacity between Manly and Cleveland.  Problems on the Cleveland line cause flow on effects as well.   
The OTR data is published on or about the 10th each month for the month preceding the last month at https://www.queenslandrail.com.au/aboutus/ourperformance/service-punctuality-and-reliability
It would be good if this delay in reporting the Monthly on-time running data could be reduced from around six weeks to two weeks as for other jurisdictions.

Reference at the RAIL Back On Track forum > https://railbotforum.org/mbs/index.php?topic=14230.0 where detailed analyses of all individual lines are available.

Robert Dow
Administration
admin@backontrack.org
RAIL Back On Track https://backontrack.org

Queensland Rail total (aggregate) results



Cleveland line on-time running

« Last Edit: April 11, 2021, 07:46:27 AM by ozbob »
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #6 on: April 11, 2021, 07:32:20 AM »
Facebook ...

Update on on-time running performance for Citytrain Queensland Rail Month of February 2021 11th April 2021 Services,...

Posted by RAIL - Back On Track on Saturday, 10 April 2021
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #7 on: April 11, 2021, 07:50:50 AM »
https://twitter.com/railbotforum/status/1381001658017009666
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

Offline achiruel

  • Member
  • *****
  • Posts: 1198
Re: Monthly line specific on-time running and reliability February 2021
« Reply #8 on: April 28, 2021, 04:13:02 AM »
Seems QR can't run on time when the trains are doing what they are designed to do, i.e. carry passengers. Running on time when practically empty isn't a great achievement.

Online ozbob

  • Administrator
  • Member
  • *****
  • Posts: 100955
    • RAIL Back On Track
Re: Monthly line specific on-time running and reliability February 2021
« Reply #9 on: April 28, 2021, 04:53:44 AM »
Yo.  Looking forward to the March OTR data.
Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  Twitter

 

Sitemap 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 


“You can't understand a city without using its public transportation system.” -- Erol Ozan