• Welcome to RAIL - Back On Track Forum.
 

17 May 2022: Contract management for new infrastructure Report

Started by ozbob, May 17, 2022, 12:18:30 PM

Previous topic - Next topic

ozbob

Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  X   Mastodon  BlueSky

ozbob

Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  X   Mastodon  BlueSky

ozbob

Half baked projects, have long term consequences ...
Ozbob's Gallery Forum   Facebook  X   Mastodon  BlueSky

ozbob

In Queensland --> Money down the drain: Auditor's damning report says govt is wasting millions

QuoteThe Queensland government's poor contract management is contributing to multimillion dollar cost blowouts and lengthy delays on major projects, according to a report from the state auditor-general.

Brendan Worrall has analysed how the Department of Energy and Public Works and Education departments, which together manage 60 per cent of government projects, handled six contracts worth a total of $1.4 billion.

Changes to the contracts after construction began increased the combined costs by $127 million and led to delays of up to four months.

The report found many of the changes were made because public servants did not manage projects effectively. ...